Tuesday, 10 December 2024
The raw water supply to the Nomlacu Water Treatment Works was restored by the evening of 9 December 2024. Operations at the Treatment Works had been temporarily interrupted due to a failure of the backup generators that supply power to the Ludeke Dam Raw Water Pump Station.
The backup generators are an interim measure to provide power to the pumps whilst the electrical transformer to the Ludeke Dam Raw Water Pump Station is being repaired.
We apologise for the inconvenience caused.
Issued by: Office of the Chief Executive, Corporate Stakeholder Management Unit